On September 30, 2023, the U.S. District Court for the District of Columbia granted summary judgment in favor of the U.S. Fish and Wildlife Service (Service) in a case challenging the agency’s final rule downlisting the American burying beetle (Nicrophorus americanus) to “threatened species” status under the Endangered Species Act (ESA).

In its opinion, the court held that the Service adhered to a reasonable interpretation of the ESA and followed proper procedures when deciding to downlist the American burying beetle to threatened status despite noting climate change ...

Ninth Circuit Holds Agency’s Decision Not to Modify a Recovery Plan is Not a Final Agency Action

Earlier this month, the U.S. Court of Appeals for the Ninth Circuit issued a ruling holding that the United States Fish and Wildlife Service’s (Service) decision not to modify a recovery plan for the grizzly bear (ursus arctos horrbilis) was not a final agency action subject to review under the Administrative Procedure Act (APA).

In 1975, the Service listed the grizzly bear as a threatened species under the Endangered Species Act (ESA).  At the time of listing, the grizzly bear’s population in the contiguous United States fell to between 700-800 individuals.  Pursuant to its ...

The U.S. Fish and Wildlife Service (Service) has issued a final rule reclassifying the Morro shoulderband snail (Helminthoglypta walkeriana) from endangered to threatened under the Endangered Species Act (ESA). The final rule also includes a rule issued under ESA section 4(d) to provide for the conservation of the species.

The Morro shoulderband snail, or banded dune snail, is a type of terrestrial snail named after the dark band on the shoulder of its shell. The species is typically found in dense clumps of grass, young patches of ice plant, and stockpiled anthropogenic ...

FWS to Assess Revisions to Mount Graham Red Squirrel’s Critical Habitat Designation

This week, the U.S. Fish and Wildlife Service (FWS) published a 12-month finding on a petition to revise the critical habitat designation for the endangered Mount Graham red squirrel (Tamiasciurus hudsonicus grahamensis) under the Endangered Species Act (ESA).  The Mount Graham red squirrel is a subspecies of red squirrel occurring only in certain high-elevation areas of the Coronado National Forest in Arizona. 

In December of 2017, a group of eNGOs including the Center for Biological Diversity submitted a petition to FWS, requesting that the agency expand the subspecies’ ...

Court Rejects Challenge to Grizzly Bear Recovery Plan

In December 2020, the United States District Court for the District of Montana issued an order on cross-motions for summary judgment concluding that it lacked jurisdiction—under both the Administrative Procedure Act (APA) and Endangered Species Act (ESA)—to hear a lawsuit involving an environmental group’s denied request to update an existing recovery plan for the grizzly bear (Ursus arctos horribilis). Ctr. for Biological Diversity v. Bernhardt, CV 19-109-M-DLC, at 26 (D. Mont. Dec. 23, 2020) (Order). After listing the grizzly bear nearly half a century ago, the U.S ...

Settlement Agreement Requires Grizzly Bear Status Review

The U.S. District Court for the District of Montana has approved a partial settlement between the Center for Biological Diversity (CBD) and the U.S. Fish and Wildlife Service (Service) requiring that the Service complete and post a status review of the lower-48 grizzly bear (Ursus arctos horribilis) populations no later than March 31, 2021.  Earlier this year, CBD filed a lawsuit challenging the Service’s alleged failure to update a 1993 federal recovery plan for the species.  The partial settlement disposes of CBD’s first claim for relief, which alleged that the Service had ...

The U.S. Fish and Wildlife Service (USFWS) is systematically revising species recovery plans issued under the Endangered Species Act (ESA).  On August 6, 2019, USFWS published three notices of availability announcing public comment periods on its draft revisions to 70 recovery plans covering 121 species across the United States ...

In its newly-released proposed recovery plan for the Desert pupfish (Cyprinodon macularius), the U.S. Fish and Wildlife Service (Service) has put into action its internal plan to add quantitative criteria to recovery plans.  The pupfish recovery plan, originally adopted in 1993, contained only qualitative criteria when adopted.  In its proposed revisions to the pupfish’s recovery plan, the Service adds quantitative criteria for whether the pupfish should be considered for delisting or when it has recovered, including the number of established populations that would make the ...

Nossaman’s Endangered Species Law & Policy blog focuses on news, events, and policies affecting endangered species issues in California and throughout the United States. Topics include listing and critical habitat decisions, conservation and recovery planning, inter-agency consultation, and related developments in law, policy, and science. We also inform readers about regulatory and legislative developments, as well as key court decisions.

Stay Connected

RSS RSS Feed

Categories

Archives

View All Nossaman Blogs
Jump to Page

We use cookies on this website to improve functionality, enhance performance, analyze website traffic and to enable social media features. To learn more, please see our Privacy Policy and our Terms & Conditions for additional detail.