Ninth Circuit Tosses NWP 12 Appeal

On August 11, 2021, the U.S. Court of Appeals for the Ninth Circuit granted partial vacatur of an appeal brought by the U.S. Army Corps of Engineers (Corps) challenging a district court decision to vacate and enjoin use of the 2017 version of nationwide permit 12 (NWP 12).

The underlying lawsuit was brought by Northern Plains Resource Council against the Corps over the Corps’ authorization of impacts to waters of the United States under NWP 12 in connection with the Keystone XL pipeline. In April 2020, the U.S. District Court for the District of Montana vacated NWP 12 throughout the ...

WEBINAR: Linear Infrastructure Redux: Adapting Your Projects to Meet the New Regulatory Climate

Linear infrastructure projects, including oil and gas pipelines, electric transmission lines and transportation, have faced a number of regulatory challenges over the last year. Some of these challenges stem from changes in regulatory schemes, adverse court holdings or drastically shifting policy initiatives. Others result from the uncertainty inherent in pending listing decisions under the Endangered Species Act, updates to the Nationwide Permitting Program under the Clean Water Act, the ever-changing definition of Waters of the United States and the Biden ...

PODCAST | Engage the Experts: The Shifting Landscape of Renewable Energy Development

We recently recorded a podcast as part of the Environmental Law Institute’s (ELI) People Places Planet Podcast series “Engage the Experts.” In our recent discussion entitled “The Shifting Landscape of Renewable Energy Development,” we discuss recent changes in environmental regulations and related court decisions that are impacting project development, as well as what this shifting terrain means for the development, expansion and maintenance of renewable energy technologies. Tune in to learn about what recent regulatory and judicial developments mean for ...

WEBINAR: Adapting Your Linear Infrastructure Projects to Changing Regulatory Frameworks

Please join us for a complimentary webinar on July 30, 2020 from 11:00 a.m. – 12:30 p.m. PT, where we will discuss the path for energy providers to move forward and reduce the risk that projects may be delayed or scrapped down the road. We will examine...

Nationwide Permit 12 (NWP 12) Vacated on ESA Grounds

On April 15, 2020, the U.S. District Court for the District of Montana issued an order that could impact energy and development projects across the United States. The court granted partial summary judgment in favor of plaintiff the Northern Plains Resource Council (“NPRC”) in a case concerning challenges to the Keystone XL Pipeline.  While the case mostly focused on the permitting for this particular pipeline, the nature of the claims raised resulted in broader implications for nationwide permit (“NWP”) 12, an important nationwide permit issued by the U.S. Army Corps of ...

Nossaman’s Endangered Species Law & Policy blog focuses on news, events, and policies affecting endangered species issues in California and throughout the United States. Topics include listing and critical habitat decisions, conservation and recovery planning, inter-agency consultation, and related developments in law, policy, and science. We also inform readers about regulatory and legislative developments, as well as key court decisions.

Stay Connected

RSS RSS Feed

Categories

Archives

View All Nossaman Blogs
Jump to Page

We use cookies on this website to improve functionality, enhance performance, analyze website traffic and to enable social media features. To learn more, please see our Privacy Policy and our Terms & Conditions for additional detail.