In Building Industry Association of the Bay Area v. U.S. Department of Commerce, a decision with significant implications for property owners, the building industry, and the development community at large, the U.S. Court of Appeals for the Ninth Circuit rejected various challenges to the National Marine Fisheries Service’s (NMFS) critical habitat designation for the southern distinct population segment of North American green sturgeon (Acipenser medirostris), holding that (1) while NMFS must consider the economic impacts of designating areas as critical habitat, NMFS is ...
In a decision that casts a shadow on the enforceability of contractual assurances in habitat conservation plan (HCP) agreements, the U.S. Court of Appeals for the Ninth Circuit rejected various Endangered Species Act (ESA) and National Environmental Policy Act (NEPA) challenges to the U.S. Fish and Wildlife Service’s (Service) designation of critical habitat for a native fish species (the Santa Ana Sucker) on the Santa Ana River in Southern California. Bear Valley Municipal Water Company v. Jewell, No. 12-57297 (9th Cir. June 25, 2015).
This is the first case to address the ...
On June 18, 2015, the U.S. District Court for the Eastern District of California denied a motion for a temporary restraining order and preliminary injunction, finding the plaintiff failed to establish that an emergency salinity barrier would imminently harm species listed under the Endangered Species Act (ESA). Center for Environmental Science, Accuracy & Reliability (CESAR) v. Cowin, No. 1:15-cv-00884-LJO-BAM (E.D. Cal Jun. 18, 2015) (pdf).
CESAR filed an action against the California Department of Water Resources (DWR) and the U.S. Fish and Wildlife Service (Service) on ...
On June 17, 2015, the U.S. Court of Appeals for the Ninth Circuit ruled that the U.S. Forest Service (Service) violated section 7 of the Endangered Species Act (ESA) by failing to reinitiate consultation with the U.S. Fish and Wildlife Service (FWS) regarding the impacts of a revised critical habitat designation on the Canada lynx (Lynx canadensis). Cottonwood Environmental Law Center v. U.S. Forest Service, No. 13-35624 (9th Cir. Jun. 17, 2015) (pdf). The Canada lynx was listed as threatened in 2000, and a limited amount of critical habitat was designated for the species in 2006 ...
On June 11, 2015, the U.S. Court of Appeals for the Ninth Circuit upheld the Bureau of Safety and Environmental Enforcement’s (Bureau) approval of oil spill response plans (OSRPs) relating to oil leases in the Beaufort and Chuckchi seas on Alaska’s Arctic coast. Alaska Wilderness League v. Jewell, No. 13-35866 (9th Cir. June 11, 2015). Among other things, environmental groups alleged that the Bureau violated the Endangered Species Act (ESA) by failing to consult regarding the impacts of the OSRPs on endangered species. The Bureau argued it was not required to consult ...
On May 27, 2015, the U.S. Court of Appeals for the Ninth Circuit provided some additional guidance as to what constitutes agency action for purposes of triggering the consultation requirement under the Endangered Species Act (ESA). The court held that although the U.S. Bureau of Land Management (BLM) was required to consult with the U.S. Fish and Wildlife Service (FWS) on the effects of a proposed road project on BLM land, BLM was not required to consult on the effects of a proposed wind project that would be accessed via the federal road project. Sierra Club v. BLM, Case No. 13-15383 ...
On Tuesday, May 26, 2015, the U.S. Court of Appeals for the District of Columbia Circuit rejected (pdf) the National Association of Home Builders’ and three other associations’ (collectively, NAHB) challenge to separate settlements between the U.S. Fish and Wildlife Service (Service) and two environmental organizations. The settlements direct the Service to make listing decisions on 251 species by specified dates. The Court of Appeals affirmed a district court’s decision that NAHB lacked standing to raise its challenge.
As we previously reported, the district court ...
In a decision issued April 28, 2015, a U.S. District Court for the District of Columbia dismissed an action challenging the U.S. Forest Service's (Service) 2012 National Forest Planning Rule (Planning Rule). The Service is responsible for managing all federally owned forest and range lands, as well as the species that reside on those lands, pursuant to a three-tiered system established by the Organic Administration Act (OAA), the Multiple-Use Sustained-Yield Act (MUSYA), and the National Forest Management Act (NFMA). This three-tier system consists of: (1) a ...
On April 17, 2015, the United States Court of Appeals for the Tenth Circuit affirmed a district court decision upholding the U.S. Fish and Wildlife Service’s (FWS) approval of a roadway project in the Rocky Flats area of Denver, Colorado. WildEarth Guardians v. U.S. Fish and Wildlife Service, Nos. 12-1508 and 12-1509, slip. op. (10th Cir. Apr. 17, 2015) (pdf). The Rocky Flats, comprised of approximately 6,200 acres in Colorado, was previously used by the Department of Energy to manufacture components of nuclear weapons. The land became polluted by various hazardous materials ...
On April 3, 2015, a federal district court in California put the brakes on a proposed logging project, invalidating a habitat conservation plan and incidental take permit issued by the U.S. Fish and Wildlife Service (FWS) and National Marine Fisheries Service (NMFS) under section 10 of the Endangered Species Act (ESA), as well as a biological opinion and incidental take statement issued by NMFS under section 7. Klamath-Siskiyou Wildlands Ctr. v. Nat’l Oceanic and Atmospheric Administration, Case No. 13-cv-03717 (N.D. Cal. Apr. 3, 2015) (pdf).
A project can avoid the general take ...
In a three-page memorandum decision, the United States Court of Appeals for the Ninth Circuit dismissed Wild Equity and other groups' appeal from a lower court decision, dismissing as moot a lawsuit alleging that the City and County of San Francisco ("San Francisco") violated the Endangered Species Act’s take prohibition as a consequence of its continuing operations of the Sharp Park Golf Course. (2015 U.S. App. LEXIS 4854 [pdf].)
The lower court dismissed the action on the grounds that the Fish and Wildlife Service issued a biological opinion and incidental take statement ...
On Friday, February 20, a federal district court denied (pdf) a motion to dismiss, thereby breathing life into an Endangered Species Act (ESA) challenge brought against the Export-Import Bank of the United States (Bank) for funding activities in and around Australia’s Great Barrier Reef World Heritage Area. See Center for Biological Diversity, et al. v. Export-Import Bank of the United States, No. C 12-6325 SBA (N.D. Cal. Feb. 20, 2015). As previously reported on this blog, the case alleges that the Bank violated section 7 of the ESA by failing to consult with federal wildlife ...
The United States District Court for the District of Columbia recently held (pdf) that the U.S. Fish and Wildlife Service (Service) violated the Endangered Species Act (ESA) when it issued a final rule delisting gray wolves in nine states (Final Rule) because the Service’s interpretation of the ESA, particularly its identification of a Distinct Population Segment (DPS) to support delisting, was unreasonable. Humane Society of the United States v. Jewell, Case No. 13-186 (D.D.C. Dec. 19, 2014).
The Final Rule, which took effect in January 2012, is the Service’s fourth ...
As numerous news outlets reported, see L.A. Times and S.F. Chronicle, the United States Court of Appeals for the Ninth Circuit issued a decision reversing a lower court and affirming a biological opinion and reasonable and prudent alternative issued by the National Marine Fisheries Service with respect to the continuing operation of the Central Valley Project by the Bureau of Reclamation and the State Water Project by the California Department of Water Resources. The Projects provide water to more than 20 million Californians.
The panel's decision relies heavily on a prior ...
A federal district court in Arkansas recently issued a decision clarifying that the obligation to consult under section 7(a)(2) of the Endangered Species Act (ESA) extends to the Small Business Administration and the Farm Service Agency when they provide loan guarantees to farmers. The case, Buffalo River Watershed Alliance v. U.S. Dept. of Agriculture, Case No. 13-450 (E.D. Ark. Dec. 2, 2014), involves a concentrated animal feeding operation in Arkansas that obtained loan guarantees from the Small Business Administration and the Farm Service Agency. The Farm Service Agency ...
On November 17, the U.S. Supreme Court denied the petition for writ of certiorari filed by Glenn Colusa Irrigation District and others seeking to overturn a decision by the United States Court of Appeals for the Ninth Circuit (en banc) holding that the Bureau of Reclamation’s decision to renew water contracts with senior water rights holders is subject to consultation under section 7(a)(2) of the Endangered Species Act. Our prior post regarding the petition is available here.
E&E reporter Jeremy Jacobs wrote in Greenwire today that the Supreme Court "left in place an ...
On November 4, 2014, the U.S. District Court for the District of Arizona issued an opinion in Ctr. for Biological Diversity v. Jewell,2014 U.S. Dist. LEXIS 157436(D. Ariz.Nov. 4, 2014) finding that the Fish and Wildlife Service (FWS) did not abuse its discretion by finding that the Sonoran Desert population of bald eagles is not a distinct population segment. The Bald eagle was originally listed as an endangered species under the precursor to the Endangered Species Act (ESA) in 1967, after FWS found that less than 500 breeding pairs remained in 1963. Under ESA protections, the bald ...
On November 4th, the U.S. District Court for the District of Utah invalidated the special rule issued by the U.S. Fish and Wildlife Service (Service) regulating take of the threatened Utah prairie dog, a species that only inhabits the state of Utah. See People for the Ethical Treatment of Property Owners v. U.S. Fish and Wildlife Serv., Case No. 2:13-cv-00278 (pdf). In 2012, the Service issued a revised special rule pursuant to section 4(d) of the Endangered Species Act (ESA) that authorized take of the species by permit only on agricultural lands, [private property] within [.5 ...
On September 23, 2014, the U.S. District Court for the District of Columbia invalidated the final rule issued by the U.S. Fish and Wildlife Service (Service) delisting the Wyoming Gray Wolf distinct population segment from the Federal List of Endangered and Threatened Species, concluding that Wyoming's regulatory protections were unenforceable and therefore inadequate for purposes of delisting the species. Despite this conclusion, the court still affirmed the Service's finding that the species has "recovered" and that it was not "endangered or threatened within a ...
Last week, the United States District Court for the Eastern District of Louisiana upheld the designation of approximately 1,544 acres of privately-owned timber land located in Louisiana as critical habitat for the dusky gopher frog (Rana sevosa), concluding that even though the frog was last spotted on the property in the 1960s and the only known wild populations of the frog are all located in the State of Mississippi, the designation by the U.S. Fish and Wildlife Service (Service) was not arbitrary or capricious. Markle Interests, LLC v. U.S. Fish and ...
In Center for Biological Diversity v. Environmental Protection Agency, No. 11-cv-00293-JCS (pdf), plaintiffs alleged that the Environmental Protection Agency (EPA) violated section 7 of the Endangered Species Act by failing to initiate and reinitiate consultation with the National Marine Fisheries and U.S. Fish and Wildlife Service with respect to its ongoing oversight of 382 active pesticide ingredients.
As previously reported, the United States District Court for the Northern District of California granted EPA’s motions to dismiss for failure to state an affirmative ...
On August 12, a judge for the Northern District of California granted (pdf) a motion to dismiss claims alleging that a federal agency violated section 7 of the Endangered Species Act (ESA) by failing to consult with federal wildlife agencies concerning the potential effects of its actions on listed species in the Great Barrier Reef.
The case concerned $4.8 billion in funding for the construction of two liquefied natural gas projects in and around Australia’s Great Barrier Reef World Heritage Area. See Center for Biological Diversity, et al. v. Export-Import Bank of the United ...
On July 14, Glenn-Colusa Irrigation District (GCID) filed a petition for writ of certiorari (pdf) with the U.S. Supreme Court, seeking review of the Ninth Circuit’s decision in Glenn-Colusa Irrigation District v. Natural Resources Defense Council, 749 F.3d 776 (9th Cir. 2014). In an en banc decision, the Ninth Circuit found that a U.S. Bureau of Reclamation (Reclamation) action renewing settlement contracts with senior water rights holders is subject to consultation under section 7(a)(2) of the Endangered Species Act (ESA), 16 U.S.C. § 1536(a)(2). The Ninth Circuit’s ...
On July 23, 2014, the United States Court of Appeals for the Tenth Circuit held that the U.S. Environmental Protection Agency (EPA) was not required to consult with the U.S. Fish and Wildlife Service regarding potential endangered species impacts of air quality regulations designed to reduce visual impacts of the Four Corners Power Plant on the Grand Canyon and other national parks. WildEarth Guardians v. EPA, 2014 U.S.App.LEXIS 13968. The court concluded that the EPA decision not to regulate air pollutants with potential to impact endangered fish was not an action subject to the ...
Last Friday, the U.S. District Court for the Eastern District of California denied (pdf) a motion brought by environmental groups to enjoin a water transfer project in the Sacramento-San Joaquin River Delta (Delta). Plaintiffs brought suit against the U.S. Bureau of Reclamation (Bureau), arguing the Bureau violated the National Environmental Policy Act (NEPA) by approving the San Luis & Delta-Mendota Water Authority (SLDMWA) Water Transfer Project, which would allow water rights holders or contractors north of the Delta to sell water to members of SLDMWA, whose members then ...
In The Aransas Project v. Shaw, the Fifth Circuit reversed a lower court’s finding that the Texas Commission on Environmental Quality violated section 9 of the Endangered Species Act through its combined actions and inactions with respect to management of water diversions in the San Antonio and Guadalupe River systems. We reported on the lower court decision here. Provided the decision stands, it suggests that the standard for liability under section 9 is not a strict liability standard, but instead requires courts to assess whether take was reasonably foreseeable drawing on common law tort principles.
On June 23, 2014, the United States District Court for the District of Columbia affirmed the strict application of the Endangered Species Act's (ESA) pre-litigation notice requirements, dismissing a lawsuit alleging that the U.S. Fish & Wildlife Service (Service) failed to timely act on a number of listing petitions because the violations stated in the pre-litigation notice and complaint did not occur until after the litigation was filed. Friends of Animals v. Ashe, No. 13-1607 (D.D.C. June 23, 2014).
Under the ESA, after a listing petition has been filed, the Service is obligated ...
Recently, the United States District Court for the District of Montana ordered (pdf) the U.S. Fish and Wildlife Service (Service) to develop a timeline for completion of recovery planning for the Canada lynx (Lynx canadensis). The court determined that the Service’s purported justifications for not developing and implementing a recovery plan for the species were insufficient in light of its statutory duty and its own internal guidelines setting forth a timetable for recovery planning.
In Friends of the Wild Swan v. Ashe, 2014 U.S. Dist. LEXIS 65378 (D. Mont. 2014), plaintiffs ...
In Souza v. California Department of Transportation, No. 13-cv-04407 (N.D. Cal. May 2, 2014), plaintiffs sought to enjoin a project proposed by the California Department of Transportation (Caltrans) to modify U.S. Route 199 and State Route 197 in Del Norte County, California, near the Smith River. Plaintiffs challenged the adequacy of Caltrans’ consultation with the National Marine Fisheries Service (Service) regarding the impacts of the project on the Southern Oregon Northern California Coast Evolutionary Significant Unit of the threatened coho salmon (SONCC coho). As ...
In a unanimous decision, eleven active judges on the United States Court of Appeals for the Ninth Circuit held that the duty to consult under section 7(a)(2) of the Endangered Species Act (ESA) when a federal agency action may affect a listed species or designated critical habitat of such species applies to the decision of the Bureau of Reclamation (Bureau) to renew long-term contracts to provide water to non-Federal parties. The decision, which reversed prior decisions by a three-judge Ninth Circuit panel and federal district court, effectively requires the Bureau to consult with the U.S. Fish and Wildlife Service (Service) regarding the effects of contract renewals on the threatened delta smelt and to renegotiate the contracts following such consultation.
The decision has potentially far-reaching implications in California because it suggests that even those who hold long-term contracts with the United States for the provision of water or senior water rights under state law must comply with the Endangered Species Act.
Last Thursday, a U.S. District Court for the Northern District of California held (pdf) that the incidental take requirements in section 7 of the Endangered Species Act (ESA) do not apply to listed plant species.
In Center for Biological Diversity v. Bureau of Land Management, No. C 03-02509 SI (N.D. Cal. Apr.3, 2014), environmental group plaintiffs challenged a biological opinion issued by the U.S. Fish and Wildlife Service (Service) to the Bureau of Land Management (BLM). BLM had engaged in section 7 consultation with the Service regarding BLM’s management of the Imperial ...
This week, the United States District Court for the District of Columbia upheld (pdf) two settlement agreements – one between the U.S. Fish and Wildlife Service (Service) and WildEarth Guardians, and the other between the Service and the Center for Biological Diversity – that collectively require the Service to determine whether to list 251 species under the Endangered Species Act (ESA) in accordance with certain deadlines. See National Association of Home Builders v. U.S. Fish and Wildlife Service, No. 12-2013 (Mar. 31, 2014). Plaintiffs, who included organizations ...
Today, the United States Court of Appeals for the Ninth Circuit issued a decision (pdf) relating to the 2008 biological opinion (BiOp) issued by the U.S. Fish and Wildlife Service (Service) regarding the effects of the Central Valley Project and State Water Project on the delta smelt. The long-awaited decision (oral argument was held on September 10, 2012) reversed in part and affirmed in part the district court’s judgment invalidating the BiOp and remanding it to the Service. The opinion is authored by Judge Bybee, with partial concurrence and partial dissent by both Judge ...
In Center for Biological Diversity v. Environmental Protection Agency, No. 11-cv-00293 (pdf), plaintiffs sued the Environmental Protection Agency (EPA), alleging that EPA’s oversight of pesticide ingredients, including trifluralin, triggered a duty to consult with the National Marine Fisheries Service about trifluralin’s possible effects on species listed under the Endangered Species Act (ESA). EPA and defendant intervenors representing the farming industry filed Rule 12(e) motions, requesting more definite statements, and alleging the complaint was so vague ...
On November 20, 2013, the United States District Court for the Southern District of California rejected a challenge by various plaintiffs and upheld the biological opinion and incidental take statement issued by the U.S. Fish and Wildlife Service (Service) for the Ocotillo Wind Energy Facility Project (Project) located in the Sonoran Desert in Imperial County, California. See The Protect Our Communities Foundation v. Ashe, No. 12-cv-2212 (S.D. Cal. Nov. 20, 2013) (pdf). The proposed Project, a utility-scale wind power project, would be comprised of 112 wind turbines ...
On November 4, 2013, the U.S. District Court for the Northern District of California approved a settlement agreement between the U.S. Fish & Wildlife Service (Service) and the Center for Biological Diversity (CBD) regarding the impacts of seven pesticides on the California red-legged frog (Rana draytonii), which is listed under the Endangered Species Act. Pursuant to the settlement, the Service is required to consult with the U.S. Environmental Protection Agency regarding whether the use of glyphosate, malathion, simazine, pendimethalin, permethrin, methomyl and ...
On August 20, 2013, the U.S. Court of Appeals for the District of Columbia held (pdf) that appellants’ claims against the U.S. Fish and Wildlife Service (Service) for an alleged failure to take certain actions under the Endangered Species Act (ESA) with respect to the straight-horned markhor (Capra falconeri jerdoni) were moot.
In 1976, the Service classified the markhor as endangered under the ESA. The species’ primary habitat is the Torghar Hills along the Pakistan-Afghanistan border. In response to the reduction of the markhor population, local tribal leaders formed ...
In American Forest Resource Council v. Ashe, 1:12-cv-00111 (D.D.C. Sept. 5, 2013), the U.S. District Court for the District of Columbia upheld the U.S. Fish & Wildlife Service’s (Service) determination that the Washington, Oregon, and California (tri-state) population of the marbled murrelet (Brachyramphus marmoratus) warrants listing under the Endangered Species Act (ESA) as a distinct population segment (DPS).
Under the ESA, three factors should be considered when determining whether a population constitutes a DPS: (1) the discreteness of the population segment in ...
On July 22, 2013, the U.S. District Court for the Western District of Washington held (pdf) that plaintiffs’ claims regarding the U.S. Fish and Wildlife Service’s (Service) alleged violation of section 10 of the Endangered Species Act (ESA) were not subject to the 60 day notice of intent to sue (NOI) requirement.
In 1997, the Washington Department of Natural Resources (DNR) adopted a habitat conservation plan to govern logging in the forests of southwest Washington. The marbled murrelet (Brachyramphus marmoratus) is one of a number of endangered and threatened species covered ...
On July 23, 2013, the U.S. Court of Appeals for the Ninth Circuit affirmed (pdf) a lower court decision upholding restrictions on commercial fishing in Alaska to protect the western Distinct Population Segment (DPS) of the Steller sea lion (Eumetopias jubatus), which is listed under the Endangered Species Act (ESA). The measures, imposed in 2010 by the National Marine Fisheries Service (NMFS), restrict the mackerel and cod fisheries in the western Aleutian Islands. NMFS determined such restrictions were necessary to ensure an adequate supply of prey for the western DPS of the ...
On July 1, 2013, the United States District Court for the Northern District of California issued an order (pdf) granting, in part, Plaintiffs’ motion for attorneys fees in Wild Equity Institute v. City and County of San Francisco, N.D. Cal. Case No. C 11-958. In the order, the court awarded plaintiffs just 25 percent of the fees requested. The court had previously dismissed the case as moot, which we reported here.
Plaintiffs initiated the lawsuit in an effort to require the City to obtain an incidental take permit under section 10 of the Endangered Species Act (ESA) for the operation of ...
The Trinity River Hatchery, which is operated by the California Department of Fish and Wildlife and funded by the U.S. Bureau of Reclamation, has a production capacity of approximately 40 million salmonid eggs. Operations at the Hatchery are intended to mitigate for lost salmonid habitat due to the construction and operation of various water projects. However, a recent lawsuit filed by the Environmental Protection Information Center alleges that instead of mitigating for impacts to endangered and threatened salmon and steelhead, the Hatchery is "taking" the protected species ...
On March 29, 2013, after more than 11 years of litigation, the United States District Court for the District of Columbia held that a defendant, as the prevailing party, was entitled to attorneys' fees under the Endangered Species Act's fee shifting provision. See Animal Welfare Institute v. Feld Entertainment, Inc., No. 03-2006 (D.D.C. Mar. 29, 2013) (pdf).
The fee provision states, in relevant part, "in issuing any final order in any suit brought" under the citizen suit provision of the Endangered Species Act, a court, in its discretion, "may award costs of ...
In Klamath Siskyou Wildlands Center v. MacWhorter, 1:12-cv-1900 (pdf), the United States District Court for the District of Oregon granted a motion to dismiss plaintiffs’ suit alleging that the U.S. Forest Service (USFS) violated the Endangered Species Act (ESA) by allowing suction dredge placer mining in the Rogue River-Siskyou National Forest without consulting with federal wildlife agencies about potential effects on coho salmon (Oncorhynchus kisutch) and coho salmon critical habitat. In dismissing the case, the court held that it lacked subject matter jurisdiction ...
In Center for Biological Diversity v. Environmental Protection Agency, the United States District Court for the Northern District of California dismissed with leave to amend (pdf) a suit alleging that the Environmental Protection Agency (EPA) violated section 7 of the Endangered Species Act (ESA) by failing to consult with the United States Fish and Wildlife Service or the National Marine Fisheries Service on the effects of 382 registered pesticides on endangered and threatened species.
The court dismissed the case, holding that plaintiffs failed to allege specific facts ...
On April 25, 2013, the United States Court of Appeals for the Ninth Circuit invalidated a consent decree that plaintiffs and three federal agency defendants asserted resolved a dispute spanning more than a decade. See Conservation Nw. v. Sherman, No. 11-35729 (9th Cir. 2013) (pdf). In doing so, the Ninth Circuit held that the district court abused its discretion when it entered the consent decree because it bypassed statutorily mandated public-participation procedures.
The Northwest Forest Plan applies to approximately 24.5 million acres of federal land ...
In American Forest Resources Council v. Ashe, 1:12-cv-00111 (D.D.C. Mar. 30, 2013), the United States District Court for the District of Columbia denied a joint motion for a consent decree regarding the critical habitat designation for the Washington, Oregon and California (tri-state) population of the marbled murrelet (Brachyramphus marmoratus).
The U.S. Fish and Wildlife Service (Service) listed the tri-state population of the marbled murrelet under the Endangered Species Act (ESA) in 1992, finding the population constituted a distinct population segment (DPS) under the ...
The Palila (Loxioides bailleui) is a small bird native to Hawaii that was listed as endangered in 1967. In 1998, the U.S. District Court for the District of Hawaii, pursuant to a stipulation submitted by the parties, issued an order requiring the State of Hawaii to conduct semi-annual "aerial sightings" for ungulates (e.g., pigs, deer, sheep, goats, cattle) in the Palila's critical habitat area. Further, if any ungulates are sighted, the order requires the State to "commence aerial shooting" of the ungulates.
In 2012, the County of Hawaii, who was not a party to the ...
On April 9, 2013, the United States District Court for the Eastern District of California ruled (pdf) on a motion (pdf) by the United States and the State of California to extend the period of time to issue new biological opinions regarding the effects of continued operation of the Central Valley Project and State Water Project on a number of fish species listed as threatened or endangered under the federal Endangered Species Act. The U.S. and California sought a three year extension of the time to issue biological opinions that were previously held to be unlawful. The court granted a ...
Nossaman’s Endangered Species Law & Policy blog focuses on news, events, and policies affecting endangered species issues in California and throughout the United States. Topics include listing and critical habitat decisions, conservation and recovery planning, inter-agency consultation, and related developments in law, policy, and science. We also inform readers about regulatory and legislative developments, as well as key court decisions.
Stay Connected
RSS FeedCategories
- Alternative Energy
- Bald and Golden Eagle Protection Act
- Budget
- CEQA
- CESA
- Climate Change
- Congress
- Conservation
- Construction Projects
- Consultation
- Continuing Education
- Court Decisions
- Critical Habitat
- Delisting
- Endangered Species Act
- Event
- Fish & Wildlife Service
- Freedom of Information Act
- Government Administration
- Legal
- Legislation
- Listing
- Litigation
- Migratory Bird
- National Marine Fisheries Service
- NEPA
- Off Shore Wind
- Pacific Northwest
- project
- Publications
- Regulatory Reform
- Sacramento-San Joaquin Delta
- SEPA
- Speaking Engagements
- Supreme Court
- Texas
- Timberland
- Water Issues